3.0 Multi-Network Project
A multi-Network project may be dened at the onset via the Project Manager.
Starting a new project, and adding the necessary number of Networks achieves this.
On the project manager side of the screen highlight ‘C-Bus
®
projects’ and then Press the Add Project
Button, this will bring up the following box. Enter a project name with a maximum of 8 characters.
Figure 5 - Add New C-Bus Project
Press the OK button and you will be asked
‘Do you want to add a Network to the new Project’.
Answering Yes will allow the addition of your rst Network, which as a default will be given a Network
address of 254.